Power conditioning needs to match the power quality environment

Voltage sags depend on the facility. An uninterruptible power supply (UPS) might be needed, but for large-scale issues, a UPS might not be the best option. See five UPS alternatives.

By Mark Stephens and Alden Wright May 6, 2020

Voltage sags have negative impacts on sensitive control circuit components and reliability. Understand the facility’s source of power to decide if the answer requires an uninterruptible power supply (UPS) or power quality mitigation technologies.  

Part 1 of this series “Why is my industrial process so sensitive to power blips?” described the power quality (PQ) event defined as a voltage sag, but known to many informally as surge, blip or outage. Part 1 also presented a typical ac control circuit and components used in many industrial processes: 120-volt control power transformer (CPT) with ac “ice cube” relay(s), programmable logic controller (PLC), adjustable speed drive (ASD), etc. The sources of process sensitivity were identified as control components vulnerable to voltage sags, or momentary reductions in supply voltage below 90% of nominal voltage. 

Below, part 2 identifies and examines possible solutions to the impact of voltage sags on sensitive control circuit components. These impacts may depend largely on the facility’s source of power. Is it supplied from a transmission circuit or a distribution circuit? Transmission systems tend to be more interconnected, and at much higher voltage levels, than distribution circuits 

What’s a voltage problem? 

Figure 1 helps illustrate the difference. With only a year of data, the system at left shows relatively shallow and brief voltage sags  all above 70% of nominal voltage and within 0.2 seconds in duration which is fairly typical of transmission systems. Critical processes succumbing to this level of PQ data are extremely sensitive.   

The PQ data (5 years) for the system at right reveals multiple interruptions at 0 voltsand many more, much deeper, and much longer voltage sags. This pattern is characteristic of distribution-fed electrical systems. Note that voltage sags above 90% of nominal, while recorded at right, should not be a problem as most equipment is designed to function normally at that level. 

Figure 2 illustrates the sensitivities of various control system components. The green, brown, red, blue, and dark green lines represent respectively a sensitive PLC, a sensitive dc power supply loaded at 100%, a sensitive ac “ice cube” relay, sensitive PLC input/output (I/O) connections, and the same sensitive dc power supply loaded at 50% of full load – a remarkable improvement merely by under loading the power supply. 

The process control circuit is most susceptible to voltage sag events largely because sophisticated power electronics – such as those found in adjustable speed drives – may require very stable voltage. Therefore, the first remedy perhaps coming to mind may be the UPS , a battery-based power supply. However, is this the best prescription for the actual problem? 

Best times to use a UPS 

For relatively brief interruptions of service, when voltage falls to zero for several minutes or even longer, a UPS may be the best choice. However, there might be other factors with respect to voltage sags. While power interruptions may demand a more comprehensive (and more expensive over the long term) PQ solution, voltage sags  far more numerous than interruptionsrequire only that additional voltage be added somehow to the process controls for the duration of the sagwhich very often remains above 50% of nominal voltage and lasts only for a half-second or less 

Bad timing 

A standby or line-interactive UPS  often chosen to save energy  may not react quickly enough to support a voltage sag perhaps because the controls may take too long to switch in for reduced voltage as opposed to a complete loss of power. By the time the UPS activates, the sag may have already concluded with the processes shutting down. In these cases, the UPS manufacturer often finds that, despite the outcome, the unit operated normally to the facility manager’s consternationHowever, a UPS in double-conversion mode (always activated) has no time lag because it is always in operation – and using more energy. 

During PQ assessments allows engineers to identify nonfunctional UPS units  often small devices “sprinkled” among control panels throughout the facility  bypassed due to dead batteries that were never maintained, apparently installed and forgotten. For a UPS to remain an effective voltage sag solution, the lead-acid batteries must be replaced every three to four years and at least checked annually 

All too often, however, the UPS is taken for granted until one day, just a few years after installation, a perhaps minor PQ event occurs that the UPS no longer is capable of mitigating. The UPS switches from a sag to an interruption. In many cases, the UPS is abandoned in place, as shown in figure 3, perhaps to avoid battery disposal costs. 

Should a UPS be necessary, a better approach would be to install a larger unit with distributed power going to those critical areas requiring it with an effective maintenance contract in place. 

Five battery-less alternatives 

Technologies exist that do not require batteries, which may be installed and forgotten (if installed correctly). These technologies, developed over the last 25 years, correct voltage to help industrial controls ride through voltage sags of 45 to 50% magnitude for one to several seconds in duration. Some also are capable of supporting momentary interruptions.  

Note that these are applied to the control circuit only and not the entire machine process; therefore, much smaller energies are involved. In one instance on a particularly problematic distribution line, one facility reduced its process shut down problem from 20 per year to five after implementing EPRI’s recommendations.  

Recommended technologies that could serve instead of a UPS can be as simple as: 

  1. Power electronic coil hold-in devices that keep relays and contactors operating through voltage sags down to 25% of nominal 
  2. The venerable ferroresonant, or constant voltage transformer (CVT), if sized correctly, can condition power to the controls through voltage sags down to 45% of nominal. Constant voltage transformerare among the heaviest and least energy efficient of battery-less voltage sag solution technologies.  
  3. Avery fast tap-changer is capable of quickly tapping up to correct the output voltage during a sag, then tapping back down when the event is over.  
  4. Astatic series compensator contains power electronic and capacitorbased energy storage.  For voltage sags above 50of nominal, the unit pulls additional current to rebuild the missing part of the waveform. For events lower in magnitude, the device uses energy from the internal storage capacitor – with proper sizing, short duration voltage interruptions can even be mitigated.  
  5. Finally, dc buffer modules based on electrolytic capacitors or ultracapacitors may support dc systems for complete interruptions ranging from 200 ms to more than 38 seconds.  

Figure 4 illustrates all of these capabilities. Unlike the UPS, these devices may operate for 10 to 15 years with little or no maintenance required. 

The importance of PQ data 

As figure 4 may illustrate, PQ data is essential for identifying the extent of PQ anomalies on the system as well as control sensitivities with some precision. The mitigation solution (or solutions) will depend on the PQ experienced at the specific site and the equipment controls under consideration. Relatively inexpensive (under $3,000 as of March 2020) and commercially available PQ meters may be obtained and installed to provide the facility managers with this important data. 

Mitigation devices may be installed approximately as indicated in figure 5. While individual control components having known sensitivities may be mitigated individually, other components with unknown sensitives may exist in the control circuit; therefore, mitigating at the CPT may be the most effective approach for making process controls more robust to voltage sags. As with most choices in the industrial environment, the true cost of the solution to a problem must be weighed with the true cost of the problem itself.

Power quality: UPS, alternatives 

After factoring in the initial costs plus including maintenance, facility managers may decide the UPS may not necessarily be the best PQ optionCareful consideration of the PQ data, the cost of the PQ problem, and the total long-term cost of the alternatives for power conditioning will lead to the best selection for PQ mitigation. Of course, every potential mitigation must include considerations for proper application and sizing – something that one learns from experience.  

While effective, these retrofit solutions might be avoided with robust control designs.  

Part 3 will examine how PQ robustness can be embedded into industrial control designs. 

Mark Stephens is principal project manager; Alden Wright is technical leader, Electric Power Research Institute (EPRI). Edited by Chris Vavra, associate editor, Control Engineering, CFE Media, cvavra@cfemedia.com 

MORE ANSWERS 

Keywords: power quality, uninterruptible power supply, UPS 

Careful consideration of the PQ data will lead to the best selection for PQ mitigation. 

For relatively brief interruptions of service, when voltage falls to zero for several minutes or longer, an uninterruptible power supply (UPS) may be the best choice. 

One of five technology alternatives to UPS may be more effective. 

Consider this 

How often does your facility check a UPS and what role do they play? 

Sidebar 

Increase uptime when PQ issues occur: 

  • Understand your PQ environment – prescribe solutions that fit your situation 
  • Don’t assume batterybased UPS systems are needed, there are other technologies 
  • Avoid use of sensitive ac components in controls  
  • Embed Robustness using ac- or dc-based controls that are compliant with IEEE 1668 Trial-Use Recommended Practice for Voltage Sag and Short Interruption Ride-Through Testing for End-Use Electrical Equipment Rated Less than 1000 V or SEMI F47 Voltage Sag Immunity Standard 
  • Utilize voltage sag ride-through settings in motordrive systems 

Visit https://mypq.epri.com or E-mail PQServices@epri.com for help in improving voltage sag robustness of your industrial automation systems.  

ONLINE extra 

https://mypq.epri.com/services/PQ_Mitigation_Technologies.mp4  

Original content can be found at Control Engineering.


Author Bio: Mark Stephens is the principal project manager; Alden Wright is technical leader, Electric Power Research Institute (EPRI).